SR 76 / I-15 Interchange Improvement

Description: In San Diego county near Bonsall and Fallbrook on Rte 15 from 0.4 mile south to 0.8 mile north of Rte 76/15 separation and on Rte 76 from 0.5 mile west to 0.5 mile east of 76/15 separation.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Bonsall, Fallbrook
Zip Code
 
Senate District
36
Assembly District 66
Congressional District 49
 
Caltrans District
11
 
 
County/State Route San Diego 15
Postmile Begin/End 46.1 47.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1132    1132  
Lane Miles Added (HOV)      N/A  
Lane Miles Added (Mixed)      N/A  
Peak Period Time Savings (minutes)  5773    5773  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Karen Jewel (619)688-6803   karen.jewel@dot.ca.gov
Design (PS&E) Phase
Caltrans Karen Jewel (619)688-6803   karen.jewel@dot.ca.gov
Right of Way Phase
Caltrans Karen Jewel (619)688-6803   karen.jewel@dot.ca.gov
Construction Phase
Caltrans Karen Jewel (619)688-6803   karen.jewel@dot.ca.gov
 
Corridor System Management Plan
Caltrans Karen Jewel (619)688-6803   karen.jewel@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$34,826 $-5,439 $29,387
Non-bond Funding
Local**
$7,362 $140 $7,502
 
Total**** $42,188 $-5,299 $36,889

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,201 $0 $3,201 $0
Design(PS&E)
$3,381 $401 $3,782 $3,782
Right of Way
$750 $-461 $289 $256
Construction
$34,856 $-5,239 $29,617 $28,716
 
Total* $42,188 $-5,299 $36,889 $32,753

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

01/20/2012 
 

 
 

01/09/2012 
100   

01/09/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/20/2011 

04/20/2012 
 

 
01/01/2011 

04/18/2012 
100  01/01/2011 

04/18/2012 


Begin Right of Way Phase

End Right of Way Phase
01/20/2011 

08/20/2012 
 

 
01/22/2011 

01/09/2012 
100  01/22/2011 

01/09/2012 


Begin Construction Phase

End Construction Phase
08/20/2012 

01/20/2015 
 

 
08/01/2012 

01/01/2015 
100  08/01/2012 

10/20/2014 


Begin Closeout Phase

End Closeout Phase
02/20/2015 

08/20/2015 
 

 
11/13/2014 

06/24/2016 
10/21/2014 

07/25/2016 


-1 
Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1132 1132
Lane Miles Added (HOV) N/A
Lane Miles Added (Mixed) N/A
Peak Period Time Savings (minutes) 5773 5773

Bond Funding Cost
Adopted:
$34,826,000
Current Approved:
$29,387,000
Actual Expenditures:
$27,084,000

 

Status as of December 31, 2023.